Wear Parts Inventory Planning

How much liner should you actually hold? The answer comes from wear rate, lead time and downtime cost — not from a rule of thumb.

Two plants running the same HP300 keep different spare strategies. One holds four mantle sets and has never stopped for a liner. The other holds one and stops twice a year waiting for a shipment. The difference is not budget — it is whether anyone calculated the number. This guide is the calculation.

The four inputs you need

You cannot plan wear parts without four numbers. If any of them is missing, the plan is a guess with a spreadsheet around it.

InputHow to get it
Wear rate (tons of liner consumed per 1,000 t crushed, or mm of wear per 1,000 t)Two measured thickness readings at known tonnage intervals
Production rate (t/h and operating hours per year)Plant records
Lead time (order to part on site, including freight and customs clearance)Actual historical shipments, not the quoted figure
Cost of downtime (per hour, or per ton of production lost)Throughput × margin, plus restart cost

Most plants have inputs two and four and are missing one and three. That is why their stock decisions default to "one spare, order when it goes in".

Step 1 · Convert wear into a replacement interval

Measure the liner thickness when new, and again after a known tonnage. The difference divided by tonnage gives a wear rate. Divide the usable thickness (new minus the minimum safe thickness) by the rate, and you have the interval in tons.

Worked example: a mantle wears 18 mm over 90,000 t. Usable thickness is 45 mm. Interval = 45 ÷ (18 ÷ 90,000) = 225,000 t. At 250 t/h and 4,000 h/year, that is 1,000,000 t/year — so roughly 4.4 months per mantle.

Two things to note. First, one measurement pair is not a wear rate, it is a data point; two or three intervals give you a range. Second, wear rate is not constant — it moves with feed gradation, moisture and closed-side setting, so re-measure after any flowsheet change.

Step 2 · Compare interval against lead time

If the replacement interval is 4.4 months and the real lead time is 3 months, you have 1.4 months of margin — and no margin at all if the shipment is delayed or the part is rejected at inspection.

The planning rule: safety stock exists to cover lead-time variability and inspection rejection, not average demand. A supplier quoting 60 days who regularly delivers in 90 needs a plan built on 90.

Step 3 · Decide between stock, buffer and contract

There are three ways to cover a replacement, and they cost differently:

  • Hold stock. Capital tied up, storage and rust risk, but the shortest response. Right when the interval is short relative to lead time and downtime cost is high.
  • Hold a production slot, not a part. Agree a scheduled production window with the foundry — the casting is made to your drawing and held as a semi-finished casting, machined on call. Cuts the response time roughly to the machining and shipping portion. This is the option most buyers never ask for.
  • Contract the reorder. Fixed price and a committed production window per interval. Cheapest per part, no capital, but no protection against your own forecast error.

For a part with a 4–6 month interval, the middle option usually wins: you avoid holding a finished 2-tonne casting for a year, but you are not starting from a bare drawing when the liner goes.

Step 4 · Size the buffer with the failure cost, not the part price

The amount of buffer is set by what a stockout costs, not by what the part costs. If one hour of downtime costs more than a liner set, holding one extra set is trivially justified. If the crusher is one of three parallel lines and the plant can absorb the loss, it is not.

A simple decision rule that holds up in practice:

Hold one set if: (downtime cost per hour × hours to source a replacement) exceeds the carrying cost of a set for its shelf life.

Step 5 · Record what actually happened

The plan is only as good as the record behind it. For each position, keep: fitted date, tonnage at changeout, wear measurement, material grade, supplier, and the reason for change (worn out, cracked, or setting change).

That record turns the next order into arithmetic instead of a phone call, and it is the only way to notice that a grade change actually helped — or did not.

What we will and will not do

We are a foundry, not a warehouse: parts are produced against order, and we will not promise stock availability we do not hold. What we can do is quote a scheduled production slot against your wear interval, agree a reorder schedule, and hold a semi-finished casting for call-off where the volume justifies it.

For the commercial side of comparing quotes, see the buying guide; for the grade decision that changes the interval itself, see the liner material guide.